Skip to content

FM200 gaseous suppression systems

FM200 cylinder bank, manifold, distribution piping and releasing panel
Representative illustration of a complete FM200 system arrangement.

About the system

Residue-free FM200 gaseous suppression for critical enclosures with electronic equipment.

System provider
Özkartay
Extinguishing agent
FM200 (HFC-227ea)

System scope

  1. Colourless, odourless and non-conductive FM200 agent
  2. Leaves no solid residue on equipment when correctly applied
  3. Cylinders may store the agent in liquid form at 25 bar
  4. Fixed nozzles, pipework, detection, warning and control panel are designed together
  5. Concentration, cylinder capacity and discharge time are calculated for the protected volume
  6. Considered for data centres, archives, museums, transformer rooms, ships and production facilities

Frequently asked questions

What is FM200?

FM200 is an HFC-227ea gaseous suppression solution that is non-conductive, colourless and odourless.

Where is FM200 used?

It is used in enclosed areas with electronic equipment, including data centres, server/UPS rooms, archives, museums, transformer rooms and critical production spaces.

Does FM200 require post-fire clean-up?

When correctly designed and discharged it leaves no solid residue; ventilation, re-entry and restart follow the project and manufacturer instructions.

How is an FM200 system sized?

The required concentration, cylinder capacity, pipe/nozzle arrangement and discharge time are calculated from the protected volume, openings, equipment and fire scenario.

Design and installation guide

FM200 gaseous suppression systems: selection and application guide

FM200 (HFC-227ea) is a clean-agent option considered for enclosed spaces where water and powder residue can be problematic. Agent quantity and distribution are determined from net volume, fire hazard, openings and the selected system design data.

FM200 (HFC-227ea) is a colourless, odourless and non-conductive gaseous suppression agent that leaves no solid residue when correctly designed. It is designed with cylinders, pipework, fixed nozzles, detection and control for enclosed areas containing electronic equipment, including data centres, server and UPS rooms, archives, museums, transformer rooms, ship engine rooms and critical production spaces.

01

Engineering and commissioning steps

Selection considers the product function, the protected risk and operating conditions together. These steps support the site survey and quotation.

  1. Defining the protected space

    Survey net room volume, raised-floor or ceiling voids, cabinets and cable penetrations. Include permanently open areas and ventilation in feasibility assessment.

  2. Agent, piping and nozzle calculations

    Determine cylinders, agent quantity, pipe route and nozzle distribution using the selected system calculation method. Pressure or discharge data from one system is not transferred to another agent or model.

  3. Detection, evacuation and interlocks

    Define detection and any cross-zone confirmation, pre-discharge warning, evacuation, manual controls and ventilation/power interlocks in the cause-and-effect scenario.

  4. Integrity and handover checks

    Check enclosure integrity and required retention conditions using the selected design tests. Calculate pressure-relief needs and hand over test records for alarms, interlocks and release controls.

02

Applications and site planning

These examples show why placement and equipment requirements can differ between facilities using the same product.

Server and control rooms

Site requirement
Electronic equipment, ventilation and cable penetrations.
Application approach
Plan enclosure integrity and power/ventilation behaviour with agent distribution calculations.

Archives and sensitive equipment spaces

Site requirement
Residue sensitivity, storage layout and enclosure openings.
Application approach
Assess fuel compatibility and agent retention together, with nozzle placement accounting for racks and equipment obstructions.

03

Pre-quotation checklist

Scroll the table horizontally to view every column.

Pre-quotation checklist
Check itemProduct / applicationInformation to assess
AgentFM200 (HFC-227ea)Hazard, system model and technical documentation
Protection boundaryDefined enclosed volumeVolume, openings and adjacent spaces
Personnel safetyEvacuation and pre-discharge warningAccess, manual controls and operating plan
CommissioningCalculations, installation and function testsEnclosure integrity, interlocks and pressure relief

Gaseous protection requires more than naming an agent and selecting cylinders. We can define the facility scope through a coordinated survey, flow calculation, detection scenario and operating-safety assessment.